NEC_PRACTICE NEC 2023

NEC 2023 Code Questions Practice Test 16

Free NEC 2023 practice test with 30 questions on solar photovoltaic (PV) systems and energy storage. Plain-English questions with full explanations.

TOPICS COVERED
NEC Practice Tests

How this test works

Read each question carefully
Look for absolute words like always / never — they often distinguish the right answer.
Manage your time
You have 45 min for 30 questions. Skip tough ones and come back.
Progress is auto-saved
Your answers are saved locally — a page refresh won't lose your work.
Review your answers
After submitting you'll see every explanation and your NEC references.

How to Use This Practice Test

This NEC 2023 Code Questions Practice Test 16 has 30 questions with detailed answers and NEC references. Take the full test, review every wrong answer, and look up the NEC article it references before moving on.

Tip: Mixed-format test — questions jump between topics just like the real exam. Don't spend more than 90 seconds on any one question.

  • Topics covered: All NEC chapters — branch circuits, grounding, conductors, wiring methods, motors, and more.
  • Passing score: Aim for 80%+ consistently before scheduling your exam.
  • Questions: 30 multiple-choice, one correct answer each
30
Questions
45 min
Time
70%
Pass

Timer starts immediately. Progress is auto-saved.

NEC_PRACTICE · NEC 2023
NEC 2023 Code Questions Practice Test 16
Q1 / 30
--:-- ON PACE
Auto-save 0% complete

0
Correct
0
Wrong
0s
Time

Student Reviews

No reviews yet — be the first to share your experience!

Leave a Review

5 stars
0/1000

NEC 2023 Code Questions Practice Test 16 — Question List

Question 1: NEC Article 690 covers the installation requirements for:

  • Solar photovoltaic power systems
  • Elevators
  • Swimming pools
  • Signs

NEC Reference: NEC 690.1

Question 2: A PV system disconnecting means must be able to disconnect:

  • All ungrounded PV conductors
  • Nothing, it stays connected always
  • Only the equipment ground
  • Only half of the panels

NEC Reference: NEC 690.13

Question 3: PV system rapid shutdown is intended mainly to protect:

  • Firefighters and emergency responders
  • The solar panels themselves
  • The utility company profits
  • Nobody, it has no purpose

NEC Reference: NEC 690.12

Question 4: Within the array boundary, rapid shutdown must reduce voltage to not more than 80 volts within:

  • 30 seconds
  • 5 minutes
  • 1 hour
  • Immediately, with zero delay

NEC Reference: NEC 690.12(B)(1)

Question 5: Exposed non-current-carrying metal parts of PV module frames and equipment must be:

  • Grounded
  • Painted
  • Left ungrounded always
  • Removed

NEC Reference: NEC 690.43

Question 6: PV circuit currents used for conductor and overcurrent device sizing are based on values that account for:

  • Irradiance and temperature effects
  • The installer's mood
  • Nothing extra, nameplate only
  • The color of the panels

NEC Reference: NEC 690.8(A)

Question 7: For PV systems on one- and two-family dwellings, the maximum system voltage is generally limited to:

  • 600 volts
  • 50 volts
  • 5000 volts
  • There is no limit

NEC Reference: NEC 690.7(C)

Question 8: A PV system disconnect must be marked to indicate it is a:

  • Photovoltaic system disconnect
  • Telephone equipment
  • Water valve
  • Nothing at all

NEC Reference: NEC 690.13(B)

Question 9: Single-conductor cable used in exposed outdoor PV source and output circuits must be listed and labeled as:

  • PV wire
  • Lamp cord
  • Bare speaker wire
  • Any random cable

NEC Reference: NEC 690.31(B)

Question 10: Interconnecting a PV inverter output to a service panel busbar is regulated by rules found in:

  • Article 705
  • Article 90
  • Article 500
  • Article 550

NEC Reference: NEC 705.12

Question 11: The sum of ampere ratings for overcurrent devices on a busbar supplied by both a feeder and a PV source generally must not exceed what percent of the busbar rating?

  • 100 %
  • 120 %
  • 150 %
  • 200 %

NEC Reference: NEC 705.12(B)(3)(2)

Question 12: A backfed circuit breaker used for a PV interconnection must be secured with:

  • A listed securing means
  • Tape only
  • Nothing, it can fall out
  • Glue

NEC Reference: NEC 705.12(B)(4)

Question 13: A permanent plaque or directory is required at electrical service equipment to indicate:

  • The location of power sources
  • The homeowner's birthday
  • Nothing at all
  • The paint brand used

NEC Reference: NEC 705.10

Question 14: NEC Article 706 covers permanently installed:

  • Energy storage systems
  • Kitchen ranges
  • Elevators
  • Swimming pools

NEC Reference: NEC 706.1

Question 15: An energy storage system needs a disconnecting means so it can be:

  • Isolated from other conductors
  • Left connected forever
  • Buried underground with no access
  • Nothing, disconnects are banned

NEC Reference: NEC 706.15

Question 16: Energy storage system equipment in dwelling units often has installation location restrictions related to:

  • Fire safety near exits and habitable rooms
  • Paint color matching
  • Nothing, any room works
  • Only bedrooms are allowed

NEC Reference: NEC 706.15

Question 17: NEC Article 705 applies to installations of:

  • Interconnected power production sources
  • Only wooden fences
  • Nothing electrical
  • Only telephone wiring

NEC Reference: NEC 705.1

Question 18: NEC Article 694 applies to:

  • Small wind electric systems
  • Gas ranges
  • Elevators
  • Swimming pools

NEC Reference: NEC 694.1

Question 19: NEC Article 692 applies to:

  • Fuel cell power systems
  • Playground lighting
  • Nothing at all
  • Telephone systems

NEC Reference: NEC 692.1

Question 20: PV modules must be marked with information including:

  • Maximum voltage and current ratings
  • The installer's favorite color
  • Nothing at all
  • The weather forecast

NEC Reference: NEC 690.51

Question 21: Rooftop PV arrays often require clear access pathways so that:

  • Firefighters can safely access the roof
  • Panels can be hidden
  • Nobody can ever access the roof
  • It has no safety purpose

NEC Reference: NEC 690.12(B)(2)

Question 22: PV system DC circuit conductors run inside a building are often required to be installed in:

  • Metal raceway or equivalent
  • Open air with no protection
  • Cardboard tubing
  • Nothing is required

NEC Reference: NEC 690.31(C)

Question 23: Rooms containing certain battery types must have ventilation to prevent buildup of:

  • Flammable gas
  • Fresh flowers
  • Sunlight
  • Nothing, ventilation is not needed

NEC Reference: NEC 480.10(A)

Question 24: A disconnecting means for a battery system must be provided to disconnect:

  • The ungrounded battery conductors
  • Nothing at all
  • Only the case
  • Only the label

NEC Reference: NEC 480.7

Question 25: A generator must generally be protected from overload by overcurrent devices or another approved means, based on its:

  • Nameplate current rating
  • Fuel tank size
  • Color
  • The manufacturer's logo

NEC Reference: NEC 445.12(A)

Question 26: A portable generator frame does not need a grounding electrode when it only supplies equipment mounted on the generator, or:

  • Cord-and-plug equipment through its own receptacles
  • The entire city grid
  • A swimming pool always
  • A hospital only

NEC Reference: NEC 250.34

Question 27: Generators should be installed in locations that provide adequate ventilation, mainly to disperse:

  • Exhaust and heat
  • Music
  • Light
  • Nothing, ventilation is unnecessary

NEC Reference: NEC 445.10

Question 28: A transfer switch for an optional standby generator system is used to prevent:

  • Interconnecting both power sources at once
  • Turning on any lights
  • Nothing, it has no purpose
  • Charging a battery

NEC Reference: NEC 702.5

Question 29: Optional standby systems are intended mainly to protect:

  • Property or business continuity
  • Nothing at all
  • Only decorative lighting
  • Neighboring homes

NEC Reference: NEC 702.2

Question 30: A PV source connected at the opposite end of a busbar from the main supply typically needs the main breaker to be:

  • Sized to meet the busbar rating rules
  • Removed completely
  • Painted a different color
  • Ignored entirely

NEC Reference: NEC 705.12(B)(2)

EXAM CARD NEC_PRACTICE
Questions30
Time limit45 min
Pass score70%
Code editionNEC 2023
DifficultyIntermediate
Last reviewedJun 2026

Timer starts immediately. Progress is auto-saved.

Source: NEC 2026 (NFPA 70)