Master Electrician Exam Cheat Sheet NEC 2026
Free printable reference — eletest.tthefl.com  ·  For study use only · Not a substitute for the NEC codebook

Transformer Sizing Formulas

Single-phase: kVA = (V × I) ÷ 1,000
Three-phase: kVA = (V × I × 1.732) ÷ 1,000

Find secondary current (3φ):

Isecondary = kVA × 1,000 ÷ (Vsec × 1.732)

Turns ratio: NP/NS = VP/VS

Motor Branch Circuit Sizing (Art. 430)

ComponentSizing Rule
Branch circuit conductorFLA × 125%
Inverse-time breaker (OCPD)FLA × 250% max
Instantaneous trip breakerFLA × 800% max (listed)
Dual-element fuseFLA × 175% max
Overload protection (SF ≥ 1.15)FLA × 115%
Overload protection (all other)FLA × 125%
Disconnecting meansHP rated, within sight of motor and controller

Service Sizing — Commercial (Art. 220)

Feeder demand factors for lighting (Table 220.42):

Portion of LoadDemand Factor
First 3,000 VA100%
Next 117,000 VA (3,001 – 120,000)35%
Over 120,000 VA25%

Optional method for dwelling units ≥ 10 kW:
Apply 40% demand factor to total load at or above 10 kW.

Three-Phase Voltage and Power

FormulaDescription
VL-L = VL-N × 1.732Line-to-line from line-to-neutral (wye)
IL = Iφ (wye)Line current = phase current in wye
VL = Vφ (delta)Line voltage = phase voltage in delta
IL = Iφ × 1.732 (delta)Line current in delta
P = V × I × 1.732 × PFThree-phase real power
kW = kVA × PFReal vs. apparent power

Conductor Ampacity — Copper (Table 310.12)

AWG / kcmil75°C Ampacity90°C Ampacity
4/0 AWG230 A260 A
250 kcmil255 A290 A
350 kcmil310 A350 A
500 kcmil380 A430 A
600 kcmil420 A475 A
750 kcmil475 A535 A

Use 75°C column for terminals rated 75°C. 90°C column only for derating calculations.

Transformer OCPD Sizing (Art. 450.3)

TypePrimary OCPDSecondary OCPD
600V and below — primary ≥ 9A125% of primary FLA125% of secondary FLA
600V and below — primary < 9A but ≥ 2A167%167%
600V and below — primary < 2A300%250%

Service Entrance Design — Key Rules (Art. 230)

RuleRequirement
Number of servicesOnly one service per building (with exceptions for large buildings, fire pumps, different voltages)
Disconnecting meansMaximum 6 disconnects grouped together at service entrance
Service clearances (overhead)3 ft minimum from windows, doors, porches; 10 ft above finished grade at entrance
Drip loopRequired at service entrance head to prevent water entry
Main bonding jumperRequired at service equipment to bond neutral to equipment ground
Surge protectionRequired at service equipment for new installations (NEC 2026 Art. 230.67)

Hazardous Locations — Classification Summary (Art. 500)

ClassHazardDivision 1Division 2
Class IFlammable gases and vaporsNormally presentPresent only during abnormal conditions
Class IICombustible dustIgnitable quantities presentPresent only during abnormal conditions
Class IIIIgnitable fibers and flyingsProduced, stored, or handledStored or handled

Class I, Division 1 = explosion-proof equipment required. Class I, Division 2 = less stringent; listed equipment required.

Generator and Emergency Systems (Art. 445, 700)

RequirementRule
Emergency system transfer timeAutomatic transfer within 10 seconds of failure (Art. 700.12)
Generator disconnecting meansRequired — within sight of generator or lockable in open position
Feeder wiring for emergency systemsMust be kept entirely independent of other wiring (Art. 700.10)
Generator output OCPD125% of nameplate current rating
Legally required standbyTransfer within 60 seconds (Art. 701)

NEC 2026 New Requirements — Master Level

ArticleNew RequirementImpact
230.67SPD required at service equipmentMust include in every new service design
625EV charging fully rewritten — V2G (bidirectional) addressedAffects load calcs for EV infrastructure
706Energy storage systems expandedBattery systems, solar+storage, disconnecting means, ventilation
210.17EV-ready outlet required in new single-family garagesDesign impact for all new residential projects

Master Exam Tips